Weekly report of Hulubalang Gold Mining Project in Indonesia(3) 2020-12-07


Basic information of Hulubalang Gold Project:

Scope of mineral rights:38.36Km2.

Mineral right type: Large gold mine.

Metal type: gold and polymetallic ores.

Location:Hulubalang Village, Paleleh Town, Central Sulawesi Province.

Project stage:Preparation period of mine construction.Infrastructure,such as surface plant,explosive magazine, dormitories and roads, has been completed.

It's time for the weekly report again. Let's see what HOT Pirates have done at the site of Hulubalang Gold Mine this week!


01

The site survey was successfully completed

After a month of site visits and field surveys, HOT has carried out GPS positioning for the locations of all the historic tunnels. The engineers entered the tunnels which met the safety conditions to collect the field data and samples on the side wall of the goaf. For the inaccessible tunnel, we can know the trend and extension of some roadways through asking the localresidents.



1607305309.jpg


02

Preliminary selection of waste dump location

With the production and operation of mine, the disposal and centralized stacking of waste should be planned well in advance, otherwise it will not only affect and destroy the surrounding ecological environment, but also affect theoperation efficiency of mines. According to the site survey, the waste dumpsite of the project is selected, which is located at the south of Hulubabang village. The area is flat, about 2 kilometers away from the mine tunnel, and there is no safety hazard to the village. Now the area has been purchased by BDLP company.

1607305385.jpg


03

View the drill core library

According to the data in the general prospecting report of No. IV deposit, 8 drillhole cores (32 in total) that have a significant impact on reserves were preliminarily determined and examined. Currently, we have done the inspection work of ZK2014 and ZK2013.


View the drill core library