Weekly report of Hulubalang Gold Mining Project in Indonesia(7) 2021-01-20
Basic information of Hulubalang Gold Project:
Scope of mineral rights:38.36Km2.
Mineral right type:Large gold mine.
Metal type:gold and polymetallic ores.
Location:Hulubalang Village, Paleleh Town, Central Sulawesi Province.
Project stage:
Preparation period of mine construction.
Infrastructure,such as surface plant,explosive magazine, dormitories and roads, has been completed.
It's time for the weekly report again. Let's see what HOT Pirates have done at the site of Hulubalang Gold Mine last week!
1、On site survey for mine construction preparation
HOT’s Engineers have surveyedthe road from the +160m adit to stockpile, took slope measurements wherethe slope was steeper, and determined the climbing ability requirements of the hauling vehicles with full load and no load.
The status of self-builtroads in mines was investigated that the self-built roads need to be repaired.
Investigation of livingquarters construction. The location and area of living quarters was determined.They surveyed a number of areas and finally decided on the location of the orebin, waste dump and parking lot.
They also visited andinvestigated the areas of air compressor and generator room.
2、Prepare the report
Our engineers have mappedand analyzed the previously data, and then prepare the reports based on theresults. At present, the community risk assessment report and the goafinvestigation report have been worked out.